Synchronous Goods Receipt for Kanban:-

With this feature,  synchronous goods receipt with the Kanban replenishment strategy In-House can be posted with Production using the control type ”Working with Production Orders for goods receipt from discrete manufacturing directly to the bin of the production supply area (PSA).

Diagram from SAP document to understand synchronous goods movement.

 

Synchronous goods movements are also supported for the following Kanban strategies:

  • Summarized JIT call (Kanban) with goods receipt from vendor directly to PSA bin.

  • Kanban replenishment strategy In-House Production using the control type Processing with Planned Orders and Cost Collector for goods receipt from repetitive manufacturing directly to the PSA bin

For this blog, Kanban Inhouse ‘0006’ Replenishment strategy has been taken.

 

Step 1:Kanban to empty →creation of production order

System will create a Production order emptying Kanban Card,

Configure all PP production order process for Auto Order release, synchronous goods posting from production scheduling profile and control cycle. Use SAP standard order type for Kanban PPK1 with Forward scheduling.

 

Step 2: Confirmation and GR of prod. order →Kanban to full

On successful Kanban confirmation, Card signal changes from Empty to Full.

System created a material document associated with Production order.

Production Order Completed.

 

Stock Updated.

Warehouse Task created & Confirmed automatically.

 

Customization Involved.

Effects on Existing Data

The system determines the goods receipt bin from the Kanban control cycle.

Effects on Customizing

 Activate synchronous goods receipt in the production scheduling profile assigned to the Kanban material:

  • In Customizing for Production under Shop Floor Control  Master Data  Define Production Scheduling Profile for Discrete Manufacturing

  • Set up several options for control of ‘Automatic Warehouse Task Creation” at storage type level or WPT level. Also determination of WPT with synchronous posting without document type and Item type

 

Thanks for reading through, I would write more stuff on EWM Manufacturing integration on S/4 HANA 2020 Embedded EWM.

Thanks to author Shailesh Mishra

Reference:https://help.sap.com/doc/474a13c5e9964c849c3a14d6c04339b5/100/en-US/363e55b4cd0a400b86f994b282cd4f7f.html

Ayhan Akkaya labelled the post as IMG — 3 years ago
3 years ago
·
#1304
0
Votes
Undo

Hello Foued,

There are 3 types of replenishment strategies which is available in kanban.

  • kanban with Stock Transfer Strategies: This is what you are describing when scanning the kanban bar code, generates a document, either WT in 2020/1909, or outbound delivery prior to 2020/1909.
  • kanban with External Procurement Strategies: This is used when emptying card directly creates Purchase order to vendor, and components are directly replenishment to PSA from vendor directly.
  • Kaban with In-House Production Strategies: The current blog explains this scenario which drives  the manufacturing of sub-assemblies or its higher assemblies getting triggered by emptying the Kanban card, meaning the signal of card drives the production process.

Best regards

Shailesh Mishra

3 years ago
·
#1303
0
Votes
Undo

Thank you for the document. However, I didn’t figure out why you have used production order to post the good movment. Normally, when you set the kanban to empty, you need a document to post the replenishment to the PSA. Could you please explain the business process behind using the production order?

 

Foued Boubaker

Ayhan Akkaya marked this post as Resolved — 3 years ago
Ayhan Akkaya labelled the post as KT - Document — 3 years ago
  • Page :
  • 1
There are no replies made for this post yet.

Bottom menu module

SAP is registered trademark of SAP AG.
EWMWIKI.COM is not affiliated to SAP AG or any of its subsidiaries.