With this feature, synchronous goods receipt with the Kanban replenishment strategy In-House can be posted with Production using the control type ”Working with Production Orders for goods receipt from discrete manufacturing directly to the bin of the production supply area (PSA).
Diagram from SAP document to understand synchronous goods movement.
Synchronous goods movements are also supported for the following Kanban strategies:
Summarized JIT call (Kanban) with goods receipt from vendor directly to PSA bin.
Kanban replenishment strategy In-House Production using the control type Processing with Planned Orders and Cost Collector for goods receipt from repetitive manufacturing directly to the PSA bin
For this blog, Kanban Inhouse ‘0006’ Replenishment strategy has been taken.
Step 1:Kanban to empty →creation of production order
System will create a Production order emptying Kanban Card,
Configure all PP production order process for Auto Order release, synchronous goods posting from production scheduling profile and control cycle. Use SAP standard order type for Kanban PPK1 with Forward scheduling.
Step 2: Confirmation and GR of prod. order →Kanban to full
On successful Kanban confirmation, Card signal changes from Empty to Full.
System created a material document associated with Production order.
Production Order Completed.
Stock Updated.
Warehouse Task created & Confirmed automatically.
Customization Involved.
The system determines the goods receipt bin from the Kanban control cycle.
Activate synchronous goods receipt in the production scheduling profile assigned to the Kanban material:
In Customizing for Production under
Thanks for reading through, I would write more stuff on EWM Manufacturing integration on S/4 HANA 2020 Embedded EWM.
Thanks to author Shailesh Mishra